Support CCJ Keep independent countywide reporting going across Collin County Back the paper built for Collin County readers Support CCJ Keep independent countywide reporting going across Collin County Back the paper built for Collin County readers Support CCJ Keep independent countywide reporting going across Collin County Back the paper built for Collin County readers

Princeton Governance

US-380 Expansion Starts Oct. 6, But the Hardest Miles Are Through Princeton

By Christian J. Remington, Editor in Chief

October 3, 2025 • 3 min read

US-380 Expansion Starts Oct. 6, But the Hardest Miles Are Through Princeton

On Monday, October 6, 2025, the U.S. 380 project moves from planning to pavement. Night work starts west of Princeton near Airport Road in McKinney and will move east in segments:

Airport → New Hope → Bridgefarmer → through Princeton → Boorman Lane.

Crews will work six nights a week, with Sundays off. Daytime lanes stay open, but traffic will be squeezed through lane shifts and construction barrels. The project is expected to take about two and a half years.

More Than Just Repaving

This is part of TxDOT’s larger plan: a new controlled-access freeway north of Princeton and a widening of the existing 380 corridor, including the stretch across Lavon Lake to CR 560.

Princeton’s segment will expand to six lanes, with frontage roads added over time.

Near-Term Impacts

Residents can expect:

Contractors must coordinate before closing side streets, though enforcement often becomes inconsistent once the work begins.

Why Now?

Traffic has long exceeded what the road was designed to handle.

TxDOT’s 2020 Feasibility Study showed Princeton carrying 49,000 vehicles per day in 2017, already near freeway capacity.

By 2045, projections reach 86,000 vehicles per day, with peak volumes potentially exceeding 100,000 daily trips.

How We Got Here

2017–2020
Feasibility study recommends a future freeway corridor.

Aug. 2, 2022
First Princeton public meeting on the project.

Sept. 12, 2024
Draft Environmental Assessment hearing.

Nov. 21, 2024
Final Environmental Assessment posted.

Dec. 27, 2024 / Jan. 6, 2025
Finding of No Significant Impact signed.

June 17, 2025
Spur 399 expansion tied to the broader 380 corridor.

Fall 2025
Princeton notice confirms the October 6 construction start.

Property Impacts

TxDOT’s Finding of No Significant Impact shows a 320- to 536-foot right-of-way corridor.

That expansion displaces:

In McKinney, Jason’s Deli, White Rhino Coffee, and 3Natives have already closed citing the project.

One Princeton family has publicly stated they are losing their home to eminent domain.

Why It Matters

Princeton, now the fastest-growing city in America, adopted a housing moratorium through November 30, 2025 because infrastructure could not keep pace with development.

The US-380 project is part of the same underlying issue: population growth moving faster than roads, utilities, and transportation planning.

What Happens Next

Night construction begins October 6 near Airport Road and will gradually move east toward Boorman Lane.

Expect closures six nights per week for roughly 2.5 years, depending on weather, utilities, and construction progress.

How Residents Can Help

Bottom Line

TxDOT promises congestion relief in two and a half years.

The Princeton Journal will track every closure, every delay, every cost, and every displacement as the project moves forward.

Published October 3, 2025. Corrections or updates will appear here.

Send this to a friend, neighbor, or someone who needs to see it.

More in Princeton Governance

Read next

These Are Princeton’s Most Dangerous Roads Right Now

April 4, 2026 • 7 min read

These Are Princeton’s Most Dangerous Roads Right Now